October 05, 2022
Distillery build update 5/10/22
Today Raymond and his crane moved our stills into position on the slab. Ric worked his magic again, getting the stills over to the island in 2 high cube containers. They were unloaded on the car park and then craned into position.
Raymond using his remote controlled crane to gently drop the wash still into place.
The bottom of the stills is pre painted with an insulating ceramic paint, this helps with efficiency and heat retention without affecting the function of the still. The wash still gently coming to rest next to the spirit, millimetre prefect.